Home Entrez le site Francais Türkçe siteye giriţ
HomeGeneral InformationServicesReferencesBoard of DirectorsContact

TREATMENT & MARINE DISPOSAL

Didim Wastewater Treatment Plant, Turkey

Project Description:

Marubeni, Garanti Bank and ABN Ambro provided financing for the municipality. TEMPO was responsible for preparing the preliminary and final designs.

Wastewater Treatment Plant:

The final design included excavation plans, road plans, plans for the storm water collection network, drainage works, landscape architecture, processing units and administration buildings. The plant was designed to handle up to 920 l/sec by the year 2020 and 1,720 l/sec by the year 2030.

The treated wastewater is discharged into the sea at a depth of 20 meters approximately 1.8 km from the shore. Sea-floor investigations and the design for the marine disposal system of the plant were carried out.

Wastewater Collection Network

The final design included a 650 km wastewater collection network. The network was designed in accordance with the latest zoning requirements and construction plans for Didim. The network consisted of diameters ranging from 300 to 1400 mm in size.

Wastewater Pump Stations

Due to the topography of the land, 15 pump stations were designed to serve the wastewater collection network. The discharges from the pump stations varied between 10 l/sec and 950 l/sec, with heads ranging between 18 m and 58 m. In addition, the design included 13 km of force mains with diameters ranging between 100 mm and 800 mm.

Client:

 VÝNSAN-DEGRÉMONT

Project Population:

 361,260 (2030)

Status:

 Completed

Marmaris Water & Wastewater Treatment Plants

Project Description:

Marubeni, Garanti Bank, Mitsubishi and ABN Ambro provided financing for the municipality concerned. TEMPO was responsible for the preparation of the preliminary and final designs of the following project components:

Water Treatment Plant:

A water treatment plant with a total capacity of 56,250 m3/day was designed to serve the projected population. The final design also included the preparation of excavation plans, road and drainage works as well as all processing units and administrative buildings.

Wastewater Treatment Plant

A tertiary wastewater treatment with a capacity of 50,626 m3/day was designed. The design also included administrative buildings, excavation works, road works, a storm water collection network, drainage works and landscape architecture.

Client:

 VÝNSAN-DEGRÉMONT

Project Population:

 375,000 (2020)

Status:

 Completed

General Information | Services | References | Board of Directors | Contact