Environmental Management References
Marmaris Environmental Project
 |
| Year |
: |
1998-2002 |
| Location |
: |
Mugla, Turkey |
| Client |
: |
Marmaris Municipality |
| Financed by |
: |
Marubeni, Garanti Bank, Mitsubishi and ABN Ambro |
| Partnership |
: |
- |
|
Main Project Features :
The design year and PE are 2020 and 250,000 PE respectively. Sub-projects in the Marmaris Environment Project are:
Water Supply System:
- Water Treatment Plant: capacity of 56.250 m³ /day
- Pumping stations: 3 units
- Water transmission main line (12 km)
- Reservoirs (for clean water): 2 units (5000 m³ and 3000 m³)
- Water distribution networks: 260 km totally
Waste Water Treatment Plant:
- Waste Water Treatment Plant: capacity of 50.626 m³ /day
- Sea Discharge: 7.2 km
Waste Water & Storm Water Cullection System:
- Waste water system: 47 km
- Storm water drainage system: 35 km
Sanitary Landfill:
- Area of the Sanitary Landfill: approx. 24 ha
- Total capacity: 1.600.000 m³
Type of Services Provided :
- Collection of Basic Data and Evaluation
- Topographical and Geotechnical Surveys
- Detailed design
- Preparation of final design
- Preparation of Bills of Quantities
Didim Environmental Project
 |
| Year |
: |
1998-2001 |
| Location |
: |
Aydin, Turkey |
| Client |
: |
Didim Municipality |
| Financed by |
: |
Marubeni, Garanti Bank, Mitsubishi and ABN Ambro |
| Partnership |
: |
- |
|
Main Project Features :
The design year and PE are 2015 and 244.350 PE, 2035 and 361.260 PE.
Sub-projects in the Didim Environment Project are described below.
Waste Water Treatment Plant:
- Treatment Plant: capacity of 920 lt/sec. (2015) ; capacity of 1,720 lt/sec. (2035)
- Sea Discharge: approx. 20 m depth, 1.8 km from the shore.
Waste Water Collection Network:
- Waste water collection network: 650 km (ø 300 mm - ø 1400 mm)
- Pumping stations: 15 units (10 lt/sec - 950 lt/sec)
- Waste water transmission line: 13 km (ø 100 mm - ø 800 mm)
Sanitary Landfill:
- Area of the Sanitary Landfill: approx. 28 ha
- Total capacity: 2,120,000 m³
Type of Services Provided :
- Data collection and evaluation
- Topographical and geotechnical site investigations
- Wastewater Treatment Plant conceptual design
- Detailed design of sanitary landfill and other sanitary systems
- Preparation of implementation projects (Sewerage System, wastewater treatment plant
- Preparation of tender specifications
- Preparation of BOQ’s.
Koycegiz - Dalyan Environmental Project
 |
| Year |
: |
1995-2005 |
| Location |
: |
Mugla, Turkey |
| Client |
: |
Ministry of Environment and Forestry, Authority for Protection of Special Areas |
| Financed by |
: |
Kreditanstalt für Wiederaufbau-KfW |
| Partnership |
: |
IGIP (DE) |
|
Main Project Features :
The design year of the project is 2025. Fullowing technical measures have been realised:
Leak detection Project for Köyceğiz:
Köyceğiz Water Supply System:
- Rehabilitation and expension of the existing water supply system of Köyceğiz
- Design capacity is 16,000 cap and 70km.
Dalyan Water Supply System:
- Construction of a new water supply system for Dalyan whose design capacity is 20,000 cap and 42 km.
Köyceğiz and Dalyan Sewerage System:
- Construction of new sewerage systems.
- Each first with about 50km
- Wastewater pump stations: 3 units (120l/sec)
Köyceğiz and Dalyan Waste Water Treatment Plant:
- Standards according to EU wastewater directive
- Population capacity: 32,000 PE (Köyceğiz), 24,000 PE (Dalyan)
Ortaca Sanitary Landfill:
- Total capacity: 500,000 m³
- Population capacity: 100,000 P.E.
- Area of the Sanitary Landfill: 3,5 ha
Type of Services Provided :
- Detailed design and preparation of tender documents on the basis of FIDIC rules (Red Book) for all physical construction measures (water, wastewater, solid waste)
- Assistance to Municipality during construction tenders
- Site supervision in compliance with FIDIC Rules.
- Tariff study and financial analyses (dynamic prime cost calculations and cash flow estimates, budget plans).
- Institutional assistance.
- Technical and non-technical training.
- Establishment of an environmental monitoring scheme and specification of related laboratory facilities and staff requirements.
|